The Reconstructing SR 32 project is necessary because the pavement on this section of SR 32—between 6th and 16th streets in Noblesville—has reached the end of its useful life and must be replaced. Properly maintaining this infrastructure asset requires replacing this section of pavement, including addressing drainage issues.
Schedule
-
PHASE 1: SR 32 at 16th Street Intersection COMPLETE
-
PHASE 2: SR 32 from 9th St to 14th St COMPLETE
-
PHASE 3: SR 32 from 6th St to 9th St COMPLETE
-
PHASE 4: SR 32 from Lakeview to 6th Street and also from 16th Street to 19th Street
-
8th Street, 10th Street, and 16th Street never closed at the same time
-
Each Phase is approximately 30-45 days